We are dedicated promoting different hydro and energy projects in Nepal. We carry out several researches, technical and economic feasibility studies, environmental and social assessments. Considering the finding of researches and studies we engage to promote different hydro projects.

People’s Power Limited is implementing the following projects :

PUWA II +

:

Puwa II Hydroelectric Project is a 4.96 MW run-of-river hydropower project being developed by People's Power Limited in Ilam District, Nepal. Located in the Sakhejung and Maipokhari areas of Ilam Municipality, the project benefits from excellent road connectivity, ensuring efficient construction and reliable long-term operation.

With an annual generation capacity of approximately 27.98 GWh of clean and renewable electricity, the project will contribute to meeting Nepal's increasing energy demand while promoting sustainable hydropower development.

Puwa II Hydroelectric Project demonstrates People's Power Limited's commitment to expanding the nation's renewable energy capacity and strengthening the national power system. Through the sustainable utilization of Nepal's abundant water resources, the project will enhance energy security, support economic growth, and contribute to a cleaner, greener, and more sustainable future.

Salient Features:

River

Puwa Khola

Municipality

Ilam (Sakhejung & Mai Pokhari)

District

Ilam

Zone

Mechi

Catchment Area

63.9 Sq Km

Design Discharge

2.72 Cum/Sec.

Marketable Annual Energy

27.98 GWh

Weir

Type of Weir

Ogee type

Size of Weir  

2.3 m length x 1.7 m width

Weir Crest Level

El. 1195 m

Flood Discharge(1:100 yrs)

348 cum/sec

Headworks

Type of intake

Side intake

Size of intake

2.0mx0.8m

Orifice Top level

El. 1195m

Gravel Trap

Section

Rectangular

Size(WxH)

5m x 3.5 m

Length

8.00 m

U/S Transition Length

3.0 m

Spillway Type

Overflow side spillway

Spillway Length

10.00 m

Gravel Flushing Gate Size

0.7 m x 0.7 m (1 number)

Headrace  Canal

Section

Rectangular covered concrete canal

Size(WxH)

1.7 m x 1.2 m

Length

270 m

Hydraulic Slope

1:500

Desanding Basin

Type               

 Dufour, Continuous/Intermittent      flushing  

Size(LefxBxH)

51.0 m x 8.0 m x 6.00 m

Transition Length

13.0 m

Desanding Chambers

2 no.

Particle Size to be settled

0.20 mm

Flushing Gate Size

1.0 m x 1.0 m (1 number)

Back Transition

Type

     Rectangular  

Size(LefxBxH)

15.00 m x 8.00 m x 6.0 m

Particle Size to be settled

less than 0.20 mm

Flushing Gate Size

0.7 m x 0.7 m (1 number)

Capacity

684.00 m3 (Volume for 3 minutes Generation)

Penstock

Type

Exposed

Material

Steel

Length

3800.00 m (uniform diameter)

Diameter

1.10 m

Thickness

8 mm to 22 mm

Powerhouse

Type of Powerhouse

Surface

Size (LxBxH)

30.00 m x 15.00 m x 15.00 m (Roof ridge)

Floor level

947.40 m

Minimum Tail water level

949.5 m

Turbine axis

953.0 m

Turbine

Type of Turbine

Pelton, Horizontal

No. of Units

2

Rated Net Head

217-239m

Unit Discharge

1.36 cum/sec

Axis

Horizontal

Rated Speed

600 rpm.

Runaway Speed

900 rpm.

Generator

Type of Generator

Synchronous AC 3 phase

Max Rated Capacity

3000 KVA

Rated Voltage

6.6 KV

Power Factor

0.85

No of pole

10

No of unit

2

Frequency

50Hz

Excitation System

Brushless

Efficiency

96%

Sub-station

Type

Outdoor

Power Transformers

6.6/33 kV, 3 phase

Type

Oil immersed self-cooled outdoor type (ONAN)

Rated Capacity

3700 kVA

Number of Units

2

Frequency

50 Hz

Number of Phase

3 phase

Voltage Ratio

6.6/33kvs

Transmission Line

About 5 km long 33 kV single circuit ACSR Dog Conductor, connected to Upper Puwa I Sub Station ACSR Dog Conductor, connected to Upper Puwa I Substation

Energy

Installed Capacity

4,960 KW

Annual Wet Energy

19.57 GWh

Annual Dry Energy

 8.41 GWh

Total Annual Energy

27.98 GWh

Financial Indicators:

Total Project Cost (Including IDC)

90 Crore

Project Financing (Debt/Equity Ratio)

2:1

Debt Interest Rate

10%

Internal Rate of Return (IRR)

14.07%

Benefit/Cost Ratio (B/C Ratio)

1.16

Project Payback Period

12 years

Gallery

Gallery Image 1

Other Projects +

Once the construction of Puwa II started, we are intensively engaged on research, assessment and study of viable projects. We are having meetings with different agencies potentially engaged on hydro project development aiming to have partnership to develop different hydro and energy projects in Nepal.

We will update about our upcoming projects once some concrete progress achieved.